|

|
Early Application:
The first
several decades of floatover were limited to projects where the
lift option was not pracitcal:
Long mobilizations
and multiple module lifts strongly favored floatover in schedule
and price. However, as the method matured it application has expanded
to nearly all regions of the world. |
Expanding
Applications:
Now, floatover
has become recognized by many companies as the base case for installations
for several reasons:
- Safety:
Consequences of failures are reduced as the Topsides is always
multiply supported between the transport vessel and substructure.
Further, there is no interim configuration between transport
and installation (installed using transport vessel).
- Schedule:
Overall schedules are shorter, as even large decks can be installed
fully commissioned, rather than by multiple module lifts and
the number and flexibility of installation vessels is greater
than for lifting.
- Economics:
Total installed cost have generally been less, as floatover
structural designs become more efficient on steel, there may
be no increase in platform cost with floatover.
- Late
Decision: Now may employ, OKI Pontoon or Dockwise
Catamaran method directly against a lift with no leg configuration
change, allowing a later term decision between lift or floatover.
Combined
these advantages have resulted in floatover expanding to almost
all parts of the world for decks as light as 1,500 T with no definite
upper limit on weight or allowable seastate. |